Resource Availability Rate

Percentage

Resource Availability Rate reveals the proportion of resources, like manpower and equipment, accessible for project tasks. It's essential for anticipating potential project delays and resourcing challenges.

Formula

Resource Availability Rate = (Available resources / Total required resources) x 100%

Example

If out of 10 needed resources, 8 are available, the resource availability rate is 80%.