Total Deviation of Time in Projects

Time

Total Deviation of Time sums the disparities between planned and actual timelines for all project tasks. It provides an aggregate view of project delays, guiding corrective actions.

Formula

Total Deviation of Time = Sum of (Actual task completion time - Planned task completion time) for all tasks

Example

If Task A is 2 days late, Task B is 1 day early, and Task C is 3 days late, the total deviation is 4 days.