Total Deviation of Time in Projects
Time
Total Deviation of Time sums the disparities between planned and actual timelines for all project tasks. It provides an aggregate view of project delays, guiding corrective actions.
Formula
Total Deviation of Time = Sum of (Actual task completion time - Planned task completion time) for all tasks
Example
If Task A is 2 days late, Task B is 1 day early, and Task C is 3 days late, the total deviation is 4 days.