Estimate To Complete

Money

Estimate To Complete (ETC) provides an estimate of the remaining costs to complete the project. This metric helps project managers adjust budgets and allocate resources efficiently.

Formula

ETC = Estimate at Completion (EAC) - Actual Cost (AC)

Example

If the EAC for a project is $250,000 and $50,000 has already been spent, the ETC is $200,000.